Thursday, May 9, 2013

Schedule as of 5/9/13


  1. Beams installed by 5/14. A sample of staining will be done for Monday meeting for color and finish approval. 
  2. Beams finished by 5/17
  3. Stucco completed by 5/23
  4. Nook ceiling insulation and patch completed. 
  5. Waiting on delivery date for laundry cabinets.
  6. Vanity tops will be installed 5/9
  7. Monday meeting we will need a location for the kitchen faucet, 
  8. Kitchen backsplash will be installed 5/11 - 5/12
  9. Door delivery date 5/17
  10. Doyle to sand and finish 5 rooms on second floor on 5/17/13
  11. Master bed room to be completed by 5/15/13. Master bath needs closet door, counter tops and trim. 
  12. GH tv. Left message with Peter Millington 
  13. GH  kitchen lighting complete. John coming this week to install 4 wall sconces. 
  14. GH kitchen ceiling complete. 
  15. GH storm door removed 
  16. pool up and running by 5/15
  17. GH Painting to be done 5/10 
  18. GH Final plumbing inspection 5/10
  19. GH Final electrical inspection 5/10
  20. GH Finish inspection 5/13