- Beams installed by 5/14. A sample of staining will be done for Monday meeting for color and finish approval.
- Beams finished by 5/17
- Stucco completed by 5/23
- Nook ceiling insulation and patch completed.
- Waiting on delivery date for laundry cabinets.
- Vanity tops will be installed 5/9
- Monday meeting we will need a location for the kitchen faucet,
- Kitchen backsplash will be installed 5/11 - 5/12
- Door delivery date 5/17
- Doyle to sand and finish 5 rooms on second floor on 5/17/13
- Master bed room to be completed by 5/15/13. Master bath needs closet door, counter tops and trim.
- GH tv. Left message with Peter Millington
- GH kitchen lighting complete. John coming this week to install 4 wall sconces.
- GH kitchen ceiling complete.
- GH storm door removed
- pool up and running by 5/15
- GH Painting to be done 5/10
- GH Final plumbing inspection 5/10
- GH Final electrical inspection 5/10
- GH Finish inspection 5/13
This blog is a way for us to keep track of everything that we talk about, suggest or do at your home over the life of our working relationship. It is updated, usually, on a daily basis during the project. Here we will record daily activity on the job, list recommendations on products and materials and add articles that pertain to your home.
Thursday, May 9, 2013
Schedule as of 5/9/13