Peter spoke with Dennis McCaffrey today and we are a go on the gas install. Details below:
- We will sign a contract on Friday 8/24.
- Nstar will cover the cost of the police detail and the permit.
- They will bring the line from about 50' in on the Fuller Village property, under the wall and to the 1431 driveway. Then they will route it to the area where the oil fills currently enter the house.
ISSUE #1 - It is possible that the town will deny the permit if the street is younger than 5 years old. At that point Archia will have to approach either the Highway Department or the DPW (or both) to state our case. This should resolve it. They may have us do an infrared repair to the paving which would be an extra cost to us.
ISSUE #2 - Nstar will not be responsible for any damage to the wall on the Fuller Hill side but do not forsee any issues. However, if there is damage the repair will be our responsibility.