Status Update 2/26/13

Tile - Starting today in baths that are ready.  Waiting on Tile confirmation for Kitchen and master bath from JB. Mudroom tile has been ordered and should be in this week.  Jambs at Offiec shower to be Carrera.  All thresholds to be Carrera.

HVAC - Radiant heat in the kitchen and the mudroom should be installed by end of day today and pressure tested.  Low profile radiators


Bath Hardware - Laura Lee and JB will be putting together a list of hardware for the baths.

Flooring - Hardwood flooring will be starting in the kitchen on Thursday or Friday.  There will be no medallion at this point.

Stucco - We will be meeting with our stucco company to look at reproducing the textured walls in the kitchen and touching up the other areas in the house next Tuesday.  

Shower Glass - Has been installed in the Guest House.


Friday, February 8, 2013

Project Notes 2/8/13

IS THERE SOMEONE TO PLOW?  STORM COMING.  There is salt and shovels on site. 

HVAC - PM has approved change order for the radiator upgrade in the guest bath and office bath.

AV - PM decided not to go with speakers in the master bedroom, master bath or office.  We will not be putting speakers in the breakfast nook but the wires will be buried in the ceiling and Folsom and Big Mike will note where they are located for future access.

Alarm - Has been installed and inspected.  Electrical inspector requested some additional basement work for safety.  Folsom will tighten up some hanging lights and wires.

Guest Bath - The expansion of the guest bath is complete with the exception of the soffiting of the ceiling over the tub.

Plaster - Plaster is moving along nicely with minor extras to date.

Carpentry - PM would like to replace the exterior door to the mudroom.  JB will give selection of style. 

Tuesday, February 5, 2013

Meeting Notes - 2/4/13

PM, PS, MN

HVAC - PM requested that Barry come to 1057 to check out duct work and system for cleaning etc.  That will happen 2/5.  
PM also requested pricing for the smaller wall hung radiators to be installed in the guest bath and the office bath.

AV - PM requested a meeting with Folsom to go over speaker and stereo locations.  PS will set up.

Plaster - We are currently well into the plaster portion of the project.  There are some fussy extras but it is mainly on course.  The 3rd floor is completed and read or paint.
Alarm - The alarm installation has started and should be done by 2/7

PlumbingThe faucet for the master bathroom tub will be on site 2/5. The plumbers can then install and the floors can be closed up.

Tile - JB will be supplying all master bath tile materials 2/6.  Tile installer will have all tile materials and specs 2/6.  Bathrooms should be ready for tile installation by early next week.
Guest Bath - Guest Bath has been demoed to the new dimensions.  Tub will be delivered on 2/7.  

Friday, December 7, 2012

Monday Meeting Notes for 12/10/12



1)      General overview and review of Kitchen and Master Bath Interiors. 
2)      Kitchen
    • Review top of Island - Wood or stone Pete is going to review with Anne.  Leaning toward stone.  PS will supply images or samples of "Super White" granite
    • Microwave in Island – drawer or door?
      Still need to confirm this.
    • Hood finish
      Still need to confirm this.
    • Confirm apron style for sink
      Still need to confirm this.
    • Pulls and hardware review
      Pete and Anne will look over options.  JB to email catalog
3)      Bar Area
    • Leaded glass for cabinet doors.
      This will be an up charge of $300.00 per door
    • Lights in upper cabinet and glass shelves.
      OK'd by client
    • Sink Finish
      Still need to confirm this.
    • Disposal in sink
      OK'd by client
    • Cabinet finish
      Still need to confirm this.  Stained or paint grade.
    • Review floor pattern
      PBS will send ideas to clients
    • Finish of woodwork and trim
      Confirmed that the transition and the area in front of the bar will all be stained trim
    • Pulls
      Pete and Anne will look over options.  JB to email catalog
4)      TV room
    • Wainscoting panel options – review and discuss
      Agreed on wainscoting option on description alone.  The panels will be similar to the cabinet doors.  The sample panel will be on site on Tuesday 12/11/12.
    • Finish – painted or stained
      All finishes in this area are to be painted except for the beams
    • AV requirements
      Still need to confirm this.
    • Stair details and finish
      Stairs will have painted risers, skirts, balusters and newels.  The handrails and newel caps are to be stained.
    • Pulls
      Pete and Anne will look over options.  JB to email catalog
5)      Hall
    • Molding profile for LED lights
      JB to send profile 
6)      Kitchen Terrace
    • Raised or at grade
      JB is working on discussed design.  Currently to be raised with steps toward yard and steps toward garage and side doors.
    • Size
      From breakfast nook to space between kitchen window and mudroom door.
    • Grill location
      To be determined.
    • Plantings
      To be determined.
7)      Master Bathroom
    • Vanity Design
      Confirmed as drawn.  Need to confirm top as stone or wood.
    • Vanity Finish
      White painted
    • Fan locations
      Confirmed that there will be 3 fans.  One in shower near door, one cetered on vanity and one in WC.  all will turn on together.
    • Pulls
      Pete and Anne will look over options.  JB to email catalog


Friday, August 17, 2012

Meeting Notes - 8/17/12

PJM, PS


  1. Cannot apply for building permit until plans and engineering is available.  JB expects them to be ready by Tuesday 8/21.
  2. Need to set up meeting with pool company to go over questions.  Including: slide, lighting, stairs.
  3. Need to set up meeting with Clients and Cabinet Co. soon to discuss details.
  4. Met with Barry Cullen.  He will start AC Installation next week.  Need to schedule meeting with PJM to discuss installation and vent locations.
  5. Existing leaded windows to be tuned up on a T&M basis.
  6. Copper estimate will be submitted next week.
  7. Still no word on gas.  Dennis McCaffery will drop in on the neighbor next week to see if he can jump start this.