Showing posts with label Main House. Show all posts
Showing posts with label Main House. Show all posts

Tuesday, August 21, 2012

This Week - 8/24/12


  1. We have started demolition on the Guest House.  
  2. Carpets have been removed in the Guest House and we have found a small area at the top of the stairs that is plywood and needs to be replaced with hardwood flooring.
  3. The bedroom window that we are repairing has significant rot.  We had planned to repair the rot damage but would like to suggest raising the window up to 6" to allow proper flashing and avoid a recurring issue.  We can discuss this at our Friday meeting.
  4. They are continuing on with demolition in the Main House.
  5. Met JB on site 8/21 and he mentioned that w should have the permit set of plans by 8/22
  6. Bees came back.  Gave them another treatment on 8/21.
  7. Barry will be submitting a proposal for installing dehumidifiers 8/21.  These will need to be installed before the mold remediation can happen and be effective.
  8. Mike will look at all of the in-ground downspout pipes to make sure they are in working order to connect to with the new downspouts.
  9. We will submit an estimate for copper and chimneys by 8/22