HVAC - PM has approved change order for the radiator upgrade in the guest bath and office bath.
AV - PM decided not to go with speakers in the master bedroom, master bath or office. We will not be putting speakers in the breakfast nook but the wires will be buried in the ceiling and Folsom and Big Mike will note where they are located for future access.
Alarm - Has been installed and inspected. Electrical inspector requested some additional basement work for safety. Folsom will tighten up some hanging lights and wires.
Guest Bath - The expansion of the guest bath is complete with the exception of the soffiting of the ceiling over the tub.
Plaster - Plaster is moving along nicely with minor extras to date.
Carpentry - PM would like to replace the exterior door to the mudroom. JB will give selection of style.