- Beams installed by 5/14. A sample of staining will be done for Monday meeting for color and finish approval.
- Beams finished by 5/17
- Stucco completed by 5/23
- Nook ceiling insulation and patch completed.
- Waiting on delivery date for laundry cabinets.
- Vanity tops will be installed 5/9
- Monday meeting we will need a location for the kitchen faucet,
- Kitchen backsplash will be installed 5/11 - 5/12
- Door delivery date 5/17
- Doyle to sand and finish 5 rooms on second floor on 5/17/13
- Master bed room to be completed by 5/15/13. Master bath needs closet door, counter tops and trim.
- GH tv. Left message with Peter Millington
- GH kitchen lighting complete. John coming this week to install 4 wall sconces.
- GH kitchen ceiling complete.
- GH storm door removed
- pool up and running by 5/15
- GH Painting to be done 5/10
- GH Final plumbing inspection 5/10
- GH Final electrical inspection 5/10
- GH Finish inspection 5/13
This blog is a way for us to keep track of everything that we talk about, suggest or do at your home over the life of our working relationship. It is updated, usually, on a daily basis during the project. Here we will record daily activity on the job, list recommendations on products and materials and add articles that pertain to your home.
Thursday, May 9, 2013
Schedule as of 5/9/13
Tuesday, April 16, 2013
Meeting Notes 4/15/13
PJM, PBS, JBC, BMN, LLW, KO,
Lighting: All fixtures are available at Granite City Electric. Big Mike will coordinate for delivery or pick up when needed.
We will supply estimate for stone floor restoration in the Hallway and Back entry.
We will supply Change order for the new Water closet at back entry/ Living room area.
We will supply an estimate for baseboard lighting at 2nd floor hallway. Propose LED tape behind molding.
We will firm up the numbers on chimney restoration. Mason meeting tomorrow.
Pool equipment will be installed on Wednesday 4/17.
Will provide landscape estimate based on meeting. Confirmed the design based on JB's design. Determined that we will leave the gate in its existing spot. Will include in removing asphalt off back corner of chauffeurs room.
Lighting: All fixtures are available at Granite City Electric. Big Mike will coordinate for delivery or pick up when needed.
We will supply estimate for stone floor restoration in the Hallway and Back entry.
We will supply Change order for the new Water closet at back entry/ Living room area.
We will supply an estimate for baseboard lighting at 2nd floor hallway. Propose LED tape behind molding.
We will firm up the numbers on chimney restoration. Mason meeting tomorrow.
Pool equipment will be installed on Wednesday 4/17.
Will provide landscape estimate based on meeting. Confirmed the design based on JB's design. Determined that we will leave the gate in its existing spot. Will include in removing asphalt off back corner of chauffeurs room.
Wednesday, April 3, 2013
Pool Tile
| Approved. Layout will be all CT TH 192 with (1) CT TH 19 DECO every 48" |
Tiling should start Friday 4/5 or Monday 4/8
Monday, April 1, 2013
Pool Finish
Please visit the link attached and choose a tile for the pool. Once you have done this we will be able to finish the pool.
http://www.classicpooltileandstone.com/index.html
http://www.classicpooltileandstone.com/index.html
Subscribe to:
Posts (Atom)