Saturday, May 19, 2012

PROJECT START - Friday 5/18/12

Meeting at 1431 Brush Hill Road  Attendees: Peter Millington, Anne Millington, Peter Stames

Archia presented a version of the contract that was to act as a intermediate contract until scope is determined and more detail on phase one can be detailed.  Updated contract and proposal is due by Friday 5/25/12.

Deposit for project ($25,000.00) was received and first installment was received ($50,000.00).