Friday, June 15, 2012

Meeting Notes - 6/15/12

Attendees: Peter Millington, Peter Stames

Change Orders - Change Orders for Basement demolition (#8), Asbestos Abatement (#7) and Garage door openers (#9) were signed.  Peter asked that we add on to the garage door project the replacement of the second torsion spring.

We discussed the basement and that after demolition we will have the abatement companies revisit for tightened quotes on the mold remediation and then we will discuss what parts of the basement will be quoted to be put back together.

Archia will provide a couple of hydrometers to keep track of humidity in the basement.  We need to confirm that the basement is always kept below 50% humidity to avoid future mold cultivation.

Archia will drain pool and set up saw horses and caution tape for safety.  This will be done on a T&M basis.

Archia submitted the proposal for the Guest House Renovation.  Waiting for client to review.

PJM would like to know if there is any way to connect the guest house to the sewer.  Chris will follow up next week.

Archia sent out email connecting Laura Lee Willard and the client for initial design meeting.