Status Update 2/26/13

Tile - Starting today in baths that are ready.  Waiting on Tile confirmation for Kitchen and master bath from JB. Mudroom tile has been ordered and should be in this week.  Jambs at Offiec shower to be Carrera.  All thresholds to be Carrera.

HVAC - Radiant heat in the kitchen and the mudroom should be installed by end of day today and pressure tested.  Low profile radiators


Bath Hardware - Laura Lee and JB will be putting together a list of hardware for the baths.

Flooring - Hardwood flooring will be starting in the kitchen on Thursday or Friday.  There will be no medallion at this point.

Stucco - We will be meeting with our stucco company to look at reproducing the textured walls in the kitchen and touching up the other areas in the house next Tuesday.  

Shower Glass - Has been installed in the Guest House.