Meeting Notes - 2/28/13

Anne and Laura Lee met this morning and (hopefully) ironed out all remaining details for the guest house. Here are the notes:

Guest House Bathroom:
  • Frost existing glass on exterior shower window
  • Paint false wall (removable panel) white to match rest of of the walls
  • LL to order all hardware including TP holder, towel bars and knobs
  • LL to order mirror - to be installed on false wall
  • Lower cabinet to be built to left of washer dryer with counter top with two doors on front for laundry product storage. Upper cabinet to continue above washer/dryer full depth for additional storage. All painted white.
Guest House Kitchen
  • LL to order hardware to match existing.
  • Cabinet around fridge?
  • Lighting fixtures are on order to be in next week
Guest House Loft
  • To be painted same as great room
  • Re-install found decorative shutters - need new hardware
  • Clean out
Guest House Great room
  • Wall sconces should be in mid-March (delayed)
Guest House Entry
  • Install wood shelf across top of closet as well as hanger bar - no closet system at this time
Guest House Bedroom
  • Install wood shelf across top of closet as well as hanger bar - no closet system at this time
  • LL to price out window treatment options