- Cannot apply for building permit until plans and engineering is available. JB expects them to be ready by Tuesday 8/21.
- Need to set up meeting with pool company to go over questions. Including: slide, lighting, stairs.
- Need to set up meeting with Clients and Cabinet Co. soon to discuss details.
- Met with Barry Cullen. He will start AC Installation next week. Need to schedule meeting with PJM to discuss installation and vent locations.
- Existing leaded windows to be tuned up on a T&M basis.
- Copper estimate will be submitted next week.
- Still no word on gas. Dennis McCaffery will drop in on the neighbor next week to see if he can jump start this.
This blog is a way for us to keep track of everything that we talk about, suggest or do at your home over the life of our working relationship. It is updated, usually, on a daily basis during the project. Here we will record daily activity on the job, list recommendations on products and materials and add articles that pertain to your home.
Friday, August 17, 2012
Meeting Notes - 8/17/12
PJM, PS