- We have started demolition on the Guest House.
- Carpets have been removed in the Guest House and we have found a small area at the top of the stairs that is plywood and needs to be replaced with hardwood flooring.
- The bedroom window that we are repairing has significant rot. We had planned to repair the rot damage but would like to suggest raising the window up to 6" to allow proper flashing and avoid a recurring issue. We can discuss this at our Friday meeting.
- They are continuing on with demolition in the Main House.
- Met JB on site 8/21 and he mentioned that w should have the permit set of plans by 8/22
- Bees came back. Gave them another treatment on 8/21.
- Barry will be submitting a proposal for installing dehumidifiers 8/21. These will need to be installed before the mold remediation can happen and be effective.
- Mike will look at all of the in-ground downspout pipes to make sure they are in working order to connect to with the new downspouts.
- We will submit an estimate for copper and chimneys by 8/22
This blog is a way for us to keep track of everything that we talk about, suggest or do at your home over the life of our working relationship. It is updated, usually, on a daily basis during the project. Here we will record daily activity on the job, list recommendations on products and materials and add articles that pertain to your home.
Tuesday, August 21, 2012
This Week - 8/24/12