This blog is a way for us to keep track of everything that we talk about, suggest or do at your home over the life of our working relationship. It is updated, usually, on a daily basis during the project. Here we will record daily activity on the job, list recommendations on products and materials and add articles that pertain to your home.
Tuesday, January 22, 2013
Hardwood Flooring
Hardwood flooring has been contracted and will start as soon as plaster is completed in each area with appropriate drying time. We will focus on the kitchen first. Once plaster is completed Barry will install the radiant subfloor and hardwood will follow directly behind him. Sanding and 2 coats of finish will follow the flooring installation. The final coat of finish will be at end of this phase of work after cabinets and appliances and painting is completed.