Wednesday, February 27, 2013

Notes 2/27/13

Tile - Met with JB on site today to go over tile layouts etc.  We clarified all areas of kitchen and master bath.  All of the tile is readily available from the Midwest and will be ordered tomorrow.

Breakfast Nook - With all of the rain we found a leak in the breakfast nook.  On further investigation we believe it was an issue with the scupper not being sealed.  This has been remedied and we will monitor it for the next few weeks to make sure that it is not recurring and that here are no other issues.
We have opened up the Sheetrock in that area to assist in drying it out and will patch next week.

Gutters & Downspouts - I had our copper company by the site today to discuss the gutter issues.  We would like to get the downspouts re-installed as soon as possible to alleviate the water infiltration in the basement.  We could do this in either copper or aluminum.  The benefits to copper are that it is inexpensive and not attractive to thieves.  The cons are that it is easily dentable and over a period of time (10 - 20 years) the aluminum will corrode because of dissimilar metals.  The aluminum will come approximately the color that the copper will patina to.  We will get a sample.

Basement Water Issue - There are areas of water in the basement as the pics below show.  We believe these are the same issues we had early on and are due to the lack of downspouts and caps on chimneys.  When the downspouts are re-installed and caps installed we will monitor to confirm our theory.

In safe room under patio.

In safe room under covered patio

Water at squash court.  Appears to be seeping in from standing water on the exterior.

Appears to be coming down chimney.
Thermostats - We have confirmed that the majority of the wiring for the thermostats is 3-wire which is what is needed for the Honeywell Wifi thermostats.  The 2-3 places that we have 2-wire are on the first floor and therefore accessible by drilling up from the basement.

Tuesday, February 26, 2013

Status Update 2/26/13

Tile - Starting today in baths that are ready.  Waiting on Tile confirmation for Kitchen and master bath from JB. Mudroom tile has been ordered and should be in this week.  Jambs at Offiec shower to be Carrera.  All thresholds to be Carrera.

HVAC - Radiant heat in the kitchen and the mudroom should be installed by end of day today and pressure tested.  Low profile radiators


Bath Hardware - Laura Lee and JB will be putting together a list of hardware for the baths.

Flooring - Hardwood flooring will be starting in the kitchen on Thursday or Friday.  There will be no medallion at this point.

Stucco - We will be meeting with our stucco company to look at reproducing the textured walls in the kitchen and touching up the other areas in the house next Tuesday.  

Shower Glass - Has been installed in the Guest House.


Friday, February 8, 2013

Project Notes 2/8/13

IS THERE SOMEONE TO PLOW?  STORM COMING.  There is salt and shovels on site. 

HVAC - PM has approved change order for the radiator upgrade in the guest bath and office bath.

AV - PM decided not to go with speakers in the master bedroom, master bath or office.  We will not be putting speakers in the breakfast nook but the wires will be buried in the ceiling and Folsom and Big Mike will note where they are located for future access.

Alarm - Has been installed and inspected.  Electrical inspector requested some additional basement work for safety.  Folsom will tighten up some hanging lights and wires.

Guest Bath - The expansion of the guest bath is complete with the exception of the soffiting of the ceiling over the tub.

Plaster - Plaster is moving along nicely with minor extras to date.

Carpentry - PM would like to replace the exterior door to the mudroom.  JB will give selection of style. 

Tuesday, February 5, 2013

Meeting Notes - 2/4/13

PM, PS, MN

HVAC - PM requested that Barry come to 1057 to check out duct work and system for cleaning etc.  That will happen 2/5.  
PM also requested pricing for the smaller wall hung radiators to be installed in the guest bath and the office bath.

AV - PM requested a meeting with Folsom to go over speaker and stereo locations.  PS will set up.

Plaster - We are currently well into the plaster portion of the project.  There are some fussy extras but it is mainly on course.  The 3rd floor is completed and read or paint.
Alarm - The alarm installation has started and should be done by 2/7

PlumbingThe faucet for the master bathroom tub will be on site 2/5. The plumbers can then install and the floors can be closed up.

Tile - JB will be supplying all master bath tile materials 2/6.  Tile installer will have all tile materials and specs 2/6.  Bathrooms should be ready for tile installation by early next week.
Guest Bath - Guest Bath has been demoed to the new dimensions.  Tub will be delivered on 2/7.  

Tuesday, January 22, 2013

Blueboard and Skim Coat Plaster

All necessary inspections have been completed.  We will commence with rock and plaster asap.  We will start in the bathrooms and jump directly on kitchen once the security issue has been rectified.

Hardwood Flooring

Hardwood flooring has been contracted and will start as soon as plaster is completed in each area with appropriate drying time.  We will focus on the kitchen first.  Once plaster is completed Barry will install the radiant subfloor and hardwood will follow directly behind him.  Sanding and 2 coats of finish will follow the flooring installation. The final coat of finish will be at end of this phase of work after cabinets and appliances and painting is completed.

Monday, January 14, 2013

Meeting Notes - 1/14/13

PM, PS, MN, MN2, JBC,

Doors - Met with Doug Handfield of LePage Windows and doors and finalized the Kitchen door with JB.  It was signed and ordered today.

Insulation - Insulation installation started today.  Will be ready for sheet rock next week.

Security - Pete is making a decision on security.  He is aware of schedule.  Needs to clarify number of smokes needed.  Big Mike will confirm with fire department.

Speakers - We confirmed that we will put 2 speakers front to back in the kitchen toward the range.  4 speakers in the sitting room.  The subwoofer will be installed into the cabinetry under the tv. Pete to supply dimensions of speakers and sub woofer.  The dining room speakers will be run from there own amp.  The wiring location is TBD.

Heat - We will remove one radiator from the staircase where it can be seen from the kitchen.  We can relocate this to the hall where the cracked radiators are located.  The other hall radiator can be replaced by the one that was removed from the mudroom.  The mudroom should be sufficiently heated by the radiant heat so no wall mounted radiator will be re-installed.

Friday, January 11, 2013

Guest House Countertops

Installed today 1/11/13

Heating issue

After receiving heat finally, yesterday, we were able to get some heat flowing to some radiators.  So far we have found 3 cracked radiators.  One in the master bath and two in the halls. The one in the master we can do without since we have another large unit and radiant heat.  The two in the halls need to be swapped out.  Barry suggests not using new radiators but making up the heat with high output baseboard elements producing high BTU's. Barry would build these himself and they would cost 60-70% less than the cost of new radiators.

The other issue involved with this is that there is asbestos wrapping both of these radiators.  We have contacted the abatement company and will have it removed.

Barry is putting together the costs to replace the heat.

Friday, January 4, 2013

Appliance final list - Confirmed and ordered 1/10/13

Double wall oven: Wolf DO30F/S 30”w stainless electric
 Refrigerator: Subzero BI30U/OLH 30”w built-in bottom mount,panel ready,interior icemaker,left hinged

Refrigerator: Subzero BI30U/ORH same as above but with right hinge
  Side x side install kit: 7004810($769) includes dual wide grille and toe kick,center trip strip,heater and hardware


 Refrigerator drawers: Subzero 700BR 27”w all refrigerator drawers,panel ready
Dishwasher: Miele G5175SCVI with the addition of China setting,hard water softening system, more flip down tynes on bottom rack and 2db quieter. These are the 2 base models, 2 or 3 models are available at higher prices
Microwave Option 1: Wolf MWD24-2U/S 24”w microwave drawer
Changed to Sharp unit

 Range top: Wolf SRT486G 48”w 6 burners with griddle,”natural” gas,comes with island trim(can choose black, red or stainless knobs)



Warming drawer: Wolf WWD30 30”wide, requires integrated drawer front(808152) for ($67) to accept custom wood panel